Monterey-Salinas Transit’s (MST) study of faster bus service and a relocated Salinas Transit Center has identified the Intermodal Transportation Center (ITC) as a leading site, while drawing questions from City Council members about Heritage Park, public event space and the project’s long-term design, during the Tuesday, Nov. 17 city council meeting.

The study, presented to the council by MST planning director Michelle Overmeyer and Adam Dankberg project manager for the consultant team hired by MST for this project, examines two proposals: moving the downtown transit center and improving bus travel along Alisal Street and Williams Road. Dankberg and Overmeyer said it gathered input from more than 800 people through surveys, focus groups and community events.

About 69 percent of survey respondents favored the ITC site, Dankberg said, citing its connections to other transportation modes and downtown destinations.

The preliminary concept would place bus bays along Market Street, using about half of the site. The remaining area could stay available for parking, events or future development, he said.

Salinas council members raised concerns that using the site could diminish Heritage Park’s role as a destination for events, including car shows and food-truck gatherings. District 6 councilmember Aurelio Salazar emphasized the welcome center, historic buildings and train museum as assets for attracting visitors. Dankberg said the proposal is still at an early stage and could be designed to integrate with the historic setting and preserve space for civic uses.

On the Alisal-Williams corridor, the study proposes dedicated bus lanes as one option. The corridor has about 1,900 daily boardings in the study area, and buses spend more than 60 percent of their time stopped by congestion, signals or passenger stops, according to Dankberg. A bus-lane option could save four to seven minutes per trip, with more than 60 percent of surveyed respondents supporting it.

Dankberg added traffic impacts from converting a lane would be minimal.

“This is a study,” Dankberg said, stressing that no funding has been secured for design or construction.

MST expects to complete the plan and share it for public review at some point in 2027.

Salazar said further discussion will be needed to balance transit access, economic development and Heritage Park’s future.